World Bank eyes 2nd extension for Cebu Bus Rapid Transit project loan

 


CEBU CITY, Cebu (PIA) -- The World Bank (WB) is eyeing to further extend the expiration date of the Cebu Bus Rapid Transit (CBRT) project loan. 

According to WB in a disclosable restructuring paper posted on its website on June 30, 2023, it has been proposed to extend the closing date by three months from June 30, 2023 to Sept. 30, 2023. 

The extension is “to allow time for the government to submit a request for restructuring of the project with necessary changes.” 

This would also allow time “to facilitate completion of activities under the current scope/design agreed during the mid-term review and thereby satisfactorily achieve the project development objective.”

“Upon receiving such request, the project could be duly restructured to facilitate completion of activities under the current scope/design agreed during the mid-term review and thereby satisfactorily achieve the project development objective,” it added. 


The P228.5-M CBRT project was approved by the World Bank Board of Executive Directors on Sept. 26, 2014. 


The project consists of $116-M from the WB, $25-M from the Clean Technology Fund (CTF), €50.89-M euros from the Agence Française de Développement (AFD) and a $30-M counterpart financing from the Philippine government.


According to the WB, $23.9-M or about 17% of the $141-M total loan commitment from IBRD and CTF has already been disbursed.


The bank noted that a “substantial” portion of the project activities may not be completed by the closing dates.


The World Bank also observed “a notable improvement” in the performance of the project under the new administration which assumed office in July 2022.


The CBRT project broke ground on Feb. 27, 2023. It  is expected to be fully operational by the second quarter of 2025, with partial operations eyed as early as the fourth quarter of 2023. 


The Cebu BRT is composed of a 13.18-kilometer bus lane in Cebu that would run from Mambaling to Cebu IT Park. 


It is seen to serve up to 160,000 passengers daily in its full operations in 2025.


President Ferdinand R. Marcos Jr. earlier led the groundbreaking rites of the CBRT Package 1 along Fuente Osmeña Circle, Cebu City on Feb. 27, 2023. 


In his speech, the President directed the Department of Transportation (DOTr) and stakeholders to ensure that the CBRT project is finished within its timeline and guarantee that informal settlers affected by the transport project will be properly relocated.


The CBRT is one of the government's flagship infrastructure projects that is designed to enhance the overall performance of the urban passenger transport system in the province of Cebu. (MYP/PIA-7 Cebu with reports from worldbank.org) 

Comments

Popular posts from this blog

Dumaguete crime rate drops

  DUMAGUETE CITY, Negros Oriental, Nov. 10 (PIA) -- The Dumaguete City Police Station has reported that between October 1 to Nov. 7, only 70 crime incidents were recorded, a decrease by 21% compared to 91 incidents in the same period of last year. In a City Peace and Order Council meeting, Lt. Col. Ronoel Fungo disclosed that no homicide, murder, robbery, carnapping, rape and rape with homicide cases were reported in the same period.  The City Health Office also reported that of the total 905 surrenderees or people who use drugs (PWUDs) in 2017, around 334 or 37% have completed their assessment as of Nov. 7, 2023. With the absence of drug dependents and pushers in Poblacion 4, 5, and 7, these are considered drug-free barangays, while Poblacion 6 was declared drug-cleared.  The City Health Office also noted that the low or no response to assessment of PWUDs are due to change of address, unknown whereabouts, conflict in work schedule, and imprisonment.  Meanwhile, the ...

POPCOM7 strengthens KATROPA implementation in CV LGUs

  (Center left) Board of Director KATROPA Danao City Federation, Juan Capuno Jr. and POPCOM KATROPA Focal Person, Roberto Yana (Center right) CEBU CITY, Cebu, March 1 (PIA) -- The Commission on Population and Development (POPCOM) Region 7 is strengthening the implementation of Kalalakin-an nga Tinud-anay sa ilang Responsibilidad og Obligasyon sa Pamilya (KATROPA) in the local government units (LGUs). During the Kapihan sa PIA, KATROPA Focal Person Roberto Yana disclosed that they aim to educate the male population of their responsibilities in the family, especially on their roles as son, husband, and father.  Members undergo a training of trainers to have a wholistic understanding of their roles and responsibilities in family planning. Yana explained that they accept members as young as 15 years old so they would be educated on community development, livelihood, and responsible parenthood.  In the same forum, Board of Director of the KATROPA Danao City Fede...

EMB 7 creates composite team for water sampling

The Environmental Management Bureau (EMB) 7 of the Department of Environment Natural Resources Central Visayas on Tuesday, Dec. 28, has created a composite team for water sampling in the different parts of the region affected by Typhoon "Odette" (International name: Rai). The EMB 7 deployed two teams conducting ambient water sampling in the Northern Cebu (Liloan area, Consolacion, Mandaue and Mactan Coastal Area) and Southern Cebu (Cebu Port Area, Talisay, Naga and San Fernando). The bureau said the first two samples from Punta Engaño near Movenpick Hotel Mactan Island Cebu and Umapad, Mandaue City near the bridge and Petron) taken last Dec. 23 and 24 were brought to Ostrea Laboratory since the EMB laboratory cannot analyze due to no electricity. The office is still awaiting the result for these two samples which will be available by Wednesday, Dec 29.  It said the other samples taken on Tuesday will also be brought to Ostrea laboratory, an accredited laboratory of EMB 7. (ID...